Permit Review Times

Building Safety is committed to providing timely plan review turn-around. See the table below for recent turn-around times and projections.

 Recent Actual Number of Workdays to Review Plan Submissions
 Month in
  Which
  Review
 Completed
Residential
Expedited
 Commercial
 Tenant
 Fit-Outs
New Homes,
 Additions &
 Remodels
Gas Risers,
 Solar Panels,
 Decks, Generators
 Jun 2018
1 - 15 days
1 - 11 days
3 -12 days
 May 2018
3 -11 days
1 - 6 days
2 -22 days
 Apr 2018
2 -10 days
1 -4 days
2 - 11 days
 Mar 2018
2 - 8 days
1 - 8 days
1 - 19 days
 Feb 2018
2 - 11 days
1 - 8 days
2 - 14 days
 Jan 2018
2 -16 days
1 - 3 days
7 - 21 days
 Dec 2017
2 - 9 days
3 - 11 days
3 - 9 days
 Nov 2017
2 - 9 days
2 - 5 days
4 - 20 days
Oct 2017
4 - 12 days
1 - 3 days
2 - 11 days
 Sep 2017
2 - 11 days
2 - 17 days
4 - 21 days
 Aug 2017
2 - 7 days
2 - 4 days
3 - 15 days
 July 2017
2 - 6 days
2 - 3 days
1 - 17 days