Sherrow Avenue Bridge

Status

This project is currently in the design phase. 

For more up to date information, visit VDOT project page Sherrow Avenue over Tripps Run Culvert Replacement in the City of Falls Church - Projects | Virginia Department of Transportation (virginiadot.org).

About the Project

This project will replace the Sherrow Avenue culvert over Tripps Run. The culvert was built in 1980. The project is 100% administered by VDOT (Virginia Department of Transportation) including design and construction.

Funding

This project is financed with federal funding.

Estimated:

Preliminary Engineering - $600,000

Right of Way Acquistion and Utility Relocation - $1.2 million

Construction - $3.3 million

Total - $5.1 million

Schedule

Begin Preliminary Engineering - July 2023

Begin Right of Way Acquisition - Late 2025

Advertise for Construction - Mid-2025

Begin Construction - Late 2026

Contact Information

For more information about this project, please contact:

Vincente Valeza, VDOT Project Manager

Ryan Borugerdi at 571-369-1787 (TTY 711), City of Falls Church POC