The project list is considered static for five years for planning and budgeting purposes. As new projects come to light they will be scored and prioritized appropriately and added to the list to be scheduled on the next cycle. If you have a stormwater project that you'd like to be considered please contact Jason Widstrom, P.E. with the Department of Public Works at 703-248-5350 (TTY 711).
    
Coe Branch Stream Restoration
  • Scope: Relocate and enhance 700 feet of Coe Branch and daylight 500 feet of stream currently piped underground
  • Cost: $1,902,434.79 (Federal Grant 55%, Local Match 45%)
  • Schedule:
    • Survey - Complete
    • Engineering Design - Complete
    • Construction start - Bridge installation August 2015
    • Project Completion - Stream portion of project completed June 2015, bridge to be installed August 2015
  • Project Manager: Jason Widstrom
  • Status: Bridge installation scheduled for August 2015.
Pearson Branch Stream Restoration
  • Scope:Stabilize and enhance 360 feet of degraded stream along Pearson Branch
  • Cost: $396,000
  • Schedule:
    • Survey - Complete
    • Engineering Design - Complete
    • Construction Start - Complete
    • Project Completion - Complete
  • Project Manager: Jason Widstrom
  • Status: Complete
City Hall Campus Water Detention Project
  • Scope: Detain stormwater runoff from City Hall campus to reduce flooding on neighboring downstream properties
  • Cost: $575,559.30
  • Schedule:
    • Survey - Complete
    • Engineering Design - Complete
    • Construction Start - Complete
    • Project Completion - Complete
  • Project Manager: Jason Widstrom
  • Status: Complete.
Wren's Branch Drainage Study (Phase 1)
  • Scope: Investigation to solve flooding problems at East Columbia and Van Buren, East Columbia and Underwood, and behind the homes on Van Buren
  • Cost: $550,000 preliminary estimate
  • Schedule:
    • Survey - Complete
    • Engineering Design - Complete
    • Construction Start - Late Spring 2016
    • Project Completion - To be Determined
  • Project Manager: Matt Hansen
  • Status: Preliminary engineer complete.
Jessie Thackery Stormwater Improvements
  • Scope: Detain stormwater runoff using large underground piping.
  • Cost: $487,567.83
  • Schedule:
      • Survey - Complete
      • Engineering Design - Complete
      • Construction Start - Complete
      • Project Completion - Complete
  • Project Manager: Jason Widstrom
  • Status: Complete
West Westmoreland Stormwater Improvements
  • Scope: Installation of new stormwater piping and inlets, bio-retention facility and potentially permeable pavers to alleviate localized flooding.
  • Cost: $120,000 Preliminary Estate
  • Schedule:
      • Survey - Undergoing
      • Engineering - Fall 2015
      • Construction Start - February/March 2016
      • Project Completion - To be determined